How a student housing developer saved $145K on a concrete podium, starting with columns already in the design

Concrete podium columns, slab and CMU elevator core during construction of a student housing building
This image may not display the actual project to keep the development anonymous.
Structure savings$145K
The projectStudent HousingMassachusettsStructure · Wood over concrete podium
TimingIn designBefore GMP pricing, no late redesign

The short version

1ProblemConcrete cores, plus extra shear walls

Most concrete podiums use concrete cores around the elevators, then add shear walls. Each extra wall means formwork and crew time.

2SignalThe columns were already in the design

Columns ran across the whole podium, tied together at every level.

3FindingFrames, not extra walls

We tied the columns and slabs into moment frames, so the building didn't need 4 to 6 concrete shear walls.

Result$145K

in structure savings, plus smaller foundations.

The project

A private college in Massachusetts partnered with a national student housing developer to add on-campus housing: two four-story, wood-framed residence halls over a concrete podium, with more than 500 beds. The architect brought us onto the team during design in 2023, as engineer of record. We came in committed to providing the most efficient design possible, studying several structural systems in schematic design: mass timber, structural steel and post-tensioned concrete. Ultimately, a post-tensioned concrete podium was selected as the ideal structural system for this project.

The hidden risk: labor

On a concrete podium, the typical way to keep the building stable against wind and earthquakes is concrete cores around the elevators, plus concrete shear walls across the floor plate. It’s a sound choice. Contractors know how to build them, they’re predictable to design, and most engineers draw them first. The hidden risk is labor, and much of it sits in the extra shear walls. Forming concrete walls is one of the most labor-intensive parts of a podium: every wall needs its own formwork and crew time. And because the walls carry so much of the load, they need large foundations beneath them. None of it shows up as its own line item when the design is chosen.

What we found

Each bar matches one finding below.

Structure savings, by finding
Finding 14 to 6 concrete shear walls
$63K · 18 ft average length
Finding 2CMU instead of concrete at the elevator cores, reduction in mat foundations
$72K · net of new CMU and footings
Finding 3Frost wall footings
$10K · 1,764 linear ft of footing
$0$50K$100K
Total: $145K.
Finding 1

The columns already in the design could replace the extra shear walls

Our team saw an opportunity to use a moment frame system with the building’s columns instead of adding concrete shear walls. The building didn’t need 4 to 6 concrete shear walls, about 18 ft long each, or the large foundations under them. The trade-off: a little more reinforcement in the columns and slabs. Savings: $63K.
Finding 1 · typical vs as built, in plan TYPICAL · CORES PLUS SHEAR WALLS AS BUILT · MOMENT FRAMES Shear walls (solid) added around the elevator cores (boxed). Large footings (dashed). Same columns, tied into frames (teal). Same cores. No shear walls, smaller footings. TYPICAL · CORES PLUS SHEAR WALLS Shear walls (solid) added around the elevator cores (boxed). Large footings (dashed). AS BUILT · MOMENT FRAMES Same columns, tied into frames (teal). Same cores. No shear walls, smaller footings.
Illustrative
Finding 2

The elevator cores were built with CMU, not cast-in-place concrete

The elevator cores were built with CMU instead of cast-in-place concrete, with a reduction in the mat foundations. Savings: $72K, net of the new CMU and footings.
Finding 2 · core wall, typical vs as built TYPICAL · CAST-IN-PLACE CONCRETE AS BUILT · CMU BLOCK Formwork on both faces, braced, then stripped (dashed). Mat foundation below. Block laid by a mason (teal). No formwork. Strip footing below. TYPICAL · CAST-IN-PLACE CONCRETE Formwork on both faces, braced, then stripped (dashed). Mat foundation below. AS BUILT · CMU BLOCK Block laid by a mason (teal). No formwork. Strip footing below.
Illustrative
Finding 3

The perimeter foundation wall didn’t need the extra steel

Around the edge of the building, a foundation wall runs below the frost line. It carries little load, but the standard design fills its footing with reinforcing steel. We took the steel out, leaving a light bar for anchoring. Savings: $10K, across 1,764 linear ft of footing.
Finding 3 · frost wall footing, typical vs as built TYPICAL · CONTINUOUS STEEL AS BUILT · LIGHT BAR ONLY grade frost line grade frost line 90° hook Bars run the full length of the footing. Wall bars hook 90° into the footing, over one light bar (teal). TYPICAL · CONTINUOUS STEEL grade frost line Bars run the full length of the footing. AS BUILT · LIGHT BAR ONLY grade frost line 90° hook Wall bars hook 90° into the footing, over one light bar (teal).
Illustrative

How we did it

  1. We mapped the columns and connections already in the design, and checked they could keep the building stable as concrete moment frames.
  2. We tested the idea with the construction team to confirm it removed labor instead of moving it.

Outcomes

Together, the three findings saved the developer $145K in structure costs: $63K from the shear walls, $72K from the elevator cores and $10K from the frost wall footings. Both buildings are complete and occupied by students.

Of course, cast-in-place concrete cores still make sense on plenty of projects. Our role is to quantify the options early so development partners can decide what works best for their project and schedule.

See what customers are saying...

We’re proud to support nationally recognized developers and architects.

“H+O is fantastic to work with; they design thoughtfully without overdoing it, and their CA process is consistently the best we’ve seen.”

Greg Procopio
Procopio Companies

“We saved steel. We saved on wood, concrete. And we were able to raise the footings a bit so that we could avoid an entire earth retention system. 

It was $500,000 saved on a $24 million project. That is real money, right?”

Dave Traggorth
Causeway Development

“Love the team at H+O Structural Engineering and can’t say enough about working with people and companies you align with. Makes work a hell of a lot easier, more fun, and produces better outcomes.”

Brent Berc
Boston Real Estate Collaborative

“H+O’s proactive communication and strong processes make sure key decisions are made on time, avoiding unnecessary setbacks and keeping projects on track.

We have confidence in H+O to not only deliver, but to think big picture, supporting long-term success beyond just one project.”

Keith Boyle
CUBE 3

“I can confidently say they’ve been an invaluable partner. They aren’t afraid to think outside the box, which has helped us optimize our structural designs and achieve greater efficiency on each project.

I highly recommend H+O to anyone looking for a reliable, innovative and collaborative partner.”

Rob Simmons
Cathartes

“H+O Cost Index is an amazing tool that is one big hammer helping us build a small city!

I will choose working smart from the start and using data to steer our decisions right the first time …..over a huge delay in our momentum to value engineer…. all day every day!”

Tony Nigro
Tuscan Village Salem

“I’m diving into his detailing to try to optimize and de-risk the plans + specs, but HE ALREADY DID IT!

2 thumbs up from me.”

Matt Calkins
TOCCI

“Really efficient, great communication and follow-up. They explain the options and impacts in a way that is easy for everyone to understand their value and make decisions.”

Robert Harbeson
Market Square Architects

“Just got a view of {the H+O Cost Index} first hand on a current project. Great tool!

Found some major savings with minimal impact to the overall design.”

Jonathan Quinn
RODE Architects

“Their ability to quickly and creatively respond to inherent challenges we encounter in the field is so important to keeping my jobs on track and moving forward.  Their collaborative approach to design, with a focus on cost efficiency and buildability, is second to none. First hand can attest to the value of the H+O Cost Index – really unique and valuable.”

I wouldn’t do a job without H+O on my team.”

Marc Savatsky
Choose Boston

“I have been fortunate to work with H+O on several wood-framed projects. I have found them to have a good understanding of how to effectively utilize offsite components in a way that brings great value to their clients.

They do a great job designing cost-effective projects that are easily constructed. I would give them a high recommendation.”

Tom Dixon
MiTek

“I can say with confidence H+O executes at a high level, regardless of the project type or location, and consistently does so in a timely manner.”

Ryan Noone
EMBARC

“I believe that most, if not all, of their structural engineers are trained to deliver a similar result that looks and feels the same. They have their systems down.”

Parker Snyder
ARCO National Construction

“They work with us, not against us. They don’t complain, bring a negative attitude, or “this is how I do it” ego. They are fresh thinking, can-do collaborators, in which we enjoy their presence as ‘designers’ on the team.”

Mike DelleFave
RODE Architects

“Great to work with the very dependable team at H+O on this new Medical building in Waltham, MA!”

Jeffry Burchard
Machado Silvetti

“As real estate developers, we are extremely grateful to have H+O in our corner. The H+O team are creative problem solvers who continuously demonstrate their value by helping us untangle complicated projects and expose the value within. We appreciate H+O’s dedication to achieving the goals of our project and we look forward to many more successful projects together.”

Dennis Kanin
New Boston Ventures